.gb-summary{max-width:880px;margin:0 auto;background:#F8FFED;border-radius:3px;padding:26px 30px;font-family:'Noto Sans KR',-apple-system,BlinkMacSystemFont,'Malgun Gothic','맑은 고딕','Apple SD Gothic Neo',sans-serif;color:#1a2733;line-height:1.6;}
.gb-summary__head{display:flex;align-items:center;justify-content:space-between;margin-bottom:16px;}
.gb-summary__label::before{content:"요약";font-size:20px;font-weight:700;color:#1a2733;letter-spacing:0.5px;}
.gb-summary__badge::after{content:"\23F0\00A0 8 min";font-size:13px;font-weight:500;color:#555;background:#ffffff;padding:4px 12px;border-radius:20px;white-space:nowrap;}
.gb-summary__list{font-size:16px;font-weight:400;color:#2c3e50;line-height:1.7;counter-reset:gbnum;padding:0 60px 0 50px;}
.gb-summary__item{margin:0 0 14px 0;padding-left:26px;text-indent:-26px;counter-increment:gbnum;}
.gb-summary__item:last-child{margin:0;}
.gb-summary__item::before{content:counter(gbnum) ".\00a0\00a0";font-weight:700;color:#1F3864;}
데이터센터 전력은 송전망·변전소·수전·변전 설비·배전의 다섯 곳을 거쳐 서버에 닿습니다.
한전 기본공급약관은 계약전력이 1만kW를 넘으면 154kV로 공급하는 것을 기본으로 둡니다. 큰 데이터센터가 전압을 낮추는 수변전 설비를 부지 안에 직접 갖추는 이유입니다.
이중 수전은 예비 선을 같은 변전소와 다른 변전소 가운데 어디서 받느냐에 따라 평소 비용과 끊김에 대비하는 정도가 다릅니다.
집에서는 플러그를 콘센트에 꽂으면 전기가 들어옵니다. 데이터센터도 같은 방식으로 전기를 받을 것처럼 보입니다. 하지만 큰 데이터센터는 동네 전봇대 선이 아니라 송전선에서 전기를 받습니다. 송전선의 높은 전압을 낮추는 설비도 데이터센터가 직접 갖춥니다. AI 서비스가 늘어 데이터센터가 커질수록 관련 소식에 변전소와 송전선이 함께 나오는 이유입니다. 이 글에서는 전기가 발전소에서 서버까지 거치는 다섯 곳을 따라가며 데이터센터가 전기를 많이 받는 방법과 끊기지 않게 받는 방법을 살펴봅니다.
데이터센터 전력이 들어오는 곳과 방식
대형 데이터센터는 송전선의 높은 전압으로 전기를 받아 건물 안 변전 설비에서 낮춘 뒤 서버까지 보냅니다.
한국전력의 기본공급약관은 한 곳에서 쓰기로 약속한 전기(계약전력)가 1만kW를 넘으면 154kV로 공급하는 것을 기본으로 정합니다¹. 계약전력이 1만kW 이하인 건물은 22.9kV 이하의 동네 배전선으로 전기를 받습니다. 1만kW를 넘는 데이터센터는 동네 배전선이 아니라 송전선 전압으로 받는 규모라는 뜻입니다.
AI용 GPU 서버를 한곳에 모으면 시설 하나에 필요한 전기가 MW(메가와트 · 1MW는 1,000kW) 단위로 커집니다. GPU 장수에서 필요한 MW를 구하는 계산은 GPU를 사 왔습니다. 그런데 이건 어디에 두나요?²에서 다뤘습니다. 시설이 커지면 계약전력이